How AQL inspection works, from sample size to final payment.

An inspector cannot open every carton. AQL sampling decides how many pieces to check and how many defects the sample may contain before the lot fails. Here is how the method works, what it does not promise, how to tie your final payment to its result, and a worked example from order to balance.

Updated 16 October 2026 · 13 min read

In short

What is an AQL inspection?

An AQL inspection checks a random sample instead of the whole order. Under ISO 2859-1, the lot size and the inspection level, usually general level II, set the sample size; the agreed AQL for each defect class sets how many defects the sample may contain. Above that number, the lot fails and the balance waits.

What AQL inspection is

AQL stands for acceptance quality limit. ISO 2859-1 sets out sampling schemes indexed by AQL for lot-by-lot inspection by attributes: each piece in the sample is judged conforming or not, and the defects are counted. Its third edition, published in January 2026, replaced the 1999 edition. Inspection companies cite it together with its American counterpart, ANSI/ASQ Z1.4.

The AQL is not a promise about the whole lot. The NIST handbook of engineering statistics describes it as the baseline quality level that a sampling plan is designed to accept with a high probability. A lot slightly worse than the AQL can still pass, and a good lot can occasionally fail: that is the price of checking a sample instead of every piece.

NIST names both risks. The producer's risk is the probability that a plan rejects a lot whose defect level equals the AQL. The consumer's risk is the probability that it accepts a lot at the LTPD, the lot tolerance percent defective, a defect level the buyer would find unacceptable. A plan's operating characteristic curve plots the probability of accepting a lot against its actual percentage of defectives, so you can see how sharply the plan separates good lots from bad ones.

This guide uses single sampling: one sample, one decision. NIST also describes double sampling, where a first sample can accept the lot, reject it or call for a second sample, and multiple sampling, which extends the idea to more than two samples.

The standard is designed for a series of lots from the same supplier. It switches to tightened inspection when quality deteriorates and allows reduced inspection when quality stays good.

Inspection level and sample size

Two inputs set the sample size: the lot size and the inspection level. There are three general levels (I, II and III) and four special levels (S-1 to S-4). Level II is the default for general consumer goods. Level I checks fewer pieces and level III more; the special levels are for cases where small samples are necessary and a larger sampling risk is acceptable.

The lot size and the level give a code letter. The code letter gives the sample size and, for each AQL, an acceptance number and a rejection number. If the sample contains no more defects than the acceptance number, that class passes; at the rejection number or above, the lot fails.

StepWorked example
Lot size5,000 units, in the 3,201 to 10,000 band
Inspection levelGeneral level II
Code letterL
Sample size200 pieces, drawn at random from the whole lot
Major defects at AQL 2.5Accepted with 10 or fewer, rejected at 11
Minor defects at AQL 4.0Accepted with 14 or fewer, rejected at 15
Critical defectsZero tolerance: one is enough to fail the lot

The sample grows much more slowly than the lot. Multiply the lot by eight and the level II sample grows by two and a half: that is why the method stays affordable on large orders, and why a small order needs a sample that is large for its size.

Inspection levelSample for 5,000 unitsSample for 40,000 units
General I80200
General II200500
General III315800
Special S-158
Special S-2813
Special S-32032
Special S-43280
  • Level II: the most widely used level, and the default for general consumer products unless something justifies a change.
  • Level III: suited to a supplier that recently had quality problems, to high-value products, and to small quantities, where the inspection takes a day whatever level you choose.
  • Level I: fewer pieces checked. Choosing it by default to save inspection time is risky.
  • Special levels: typically used for tests that take a long time or destroy the samples, and during container loading supervision.

A larger sample takes more inspection time and gives a sharper answer. The level is a choice about risk, not only about cost.

Critical, major and minor defects

Defects are sorted into classes before the inspection, and each class gets its own AQL.

  • Critical: a safety or compliance failure, a product that could hurt the user or break the rules of the destination market.
  • Major: a defect that affects function or appearance enough that the customer would likely return the product.
  • Minor: a small cosmetic defect that does not affect function.
Defect classCommon AQL, low and medium value goodsCommon AQL, high value goods
Critical00
Major2.51.0 or 1.5
Minor4.02.5 or 4.0

The classes only work if the defect list is specific. For a desk lamp, for instance, an exposed live wire would be critical; a lamp that does not switch on, or a deep scratch visible at arm's length, major; a small mark on the underside, minor. Describe each defect in words, add photos of the limit you accept, and say at what distance and under what light appearance is judged.

These values are common practice among inspection companies, not a requirement of the standard. The buyer chooses them and writes them into the order, together with a defect list that says which defect belongs to which class.

When to inspect

  1. 01

    Pre-production check

    At the start of production, also called an initial production check: raw materials, components and the production setup, before the full quantity is made.

  2. 02

    During production

    While the lines are running: defects, delays and process problems found while they can still be corrected.

  3. 03

    Pre-shipment inspection

    When production is complete and at least 80% of the goods are packed, so the sample comes from the finished lot. This is the AQL inspection most buyers link to the balance.

  4. 04

    Container loading check

    At loading: products, quantities, packaging condition and carton marks, the cleanliness of the container and the way the goods are stowed.

A first order with a new supplier, or a product with safety-critical features, justifies more than one stage. A repeat order from a supplier with a clean record may need only the pre-shipment inspection.

Book the pre-shipment inspection against the production schedule, not the shipping date. If the goods are not finished and mostly packed on the day, the inspector samples a lot that does not yet exist, and the report says little about what will be shipped.

What an inspection report contains

  • The order reference, the quantity found against the quantity ordered, and the sampling plan applied: lot size, level, sample size and AQL per class.
  • Packaging, labelling and shipping marks, barcodes included, checked against your instructions.
  • Workmanship and appearance, with every defect counted, classified critical, major or minor, and photographed.
  • Function tests, measurements and on-site tests such as carton drop tests, as the checklist requires.
  • A result for each checkpoint and an overall pass or fail against the agreed AQL.

Read it in that order. A pass on a sample drawn from half the quantity, or on the wrong sampling plan, is not the pass you asked for. Then compare each defect count with the acceptance number, look at the photos of the defects the inspector classified, and check that every test on your list was actually carried out.

A report is only as good as its reference. Give the inspector the approved sample, the specifications and the defect list before the visit.

Tie the balance to a passed inspection

An inspection protects you only while money still depends on it. A common structure is a deposit before production and the balance once the goods are ready; the safer version makes the balance due after the pre-shipment inspection. A pass then gives you documented evidence of quality before you pay, and a fail gives you independent evidence to demand corrections before you settle.

  • The plan: ISO 2859-1, general inspection level II, and the AQL for each defect class.
  • The reference: approved sample, specifications, packaging instructions and defect list.
  • The trigger: the balance is due within a set number of days after a report with an overall pass.
  • The failure path: sorting or rework by the supplier, then a new inspection, with who pays for it stated in advance.
  • Access: the inspector picks the cartons at random, and the factory provides space, tools and staff to open them.

A worked example: from order to balance

Illustrative example. The importer, the product and every count below are hypothetical. The sampling figures are those of the ISO 2859-1 tables for a lot of this size.

Company C orders 4,000 desk lamps, with a 30% deposit and the balance due after a passed pre-shipment inspection. The order specifies general level II and AQLs of 0, 2.5 and 4.0. A lot of 4,000 falls in the 3,201 to 10,000 band, so the code letter is L and the inspector draws 200 lamps: up to 10 major and 14 minor defects are accepted, and no critical defect. The function test runs on 20 lamps, special level S-3.

CheckFirst inspectionRe-inspection
Critical defects (none accepted)00
Major defects (up to 10 accepted)74
Minor defects (up to 14 accepted)179
Function test on 20 lampsAll passAll pass
Overall resultFail, on minor defectsPass

The first inspection fails on minor defects alone: 17 is above the acceptance number of 14. Company C does not pay the balance. The supplier sorts the lot and reworks the marked bases, and a new inspector draws a fresh random sample of 200. The second report passes, and Company C pays the balance within the period set in the contract. Because the contract put the cost of a re-inspection on the supplier, the second visit cost Company C nothing.

Common mistakes, and how to avoid them

  • Letting the factory choose the cartons. A sample chosen by the factory tells you about the pieces it chose. The inspector draws at random from the whole lot.
  • Inspecting too early. Before production is complete and at least 80% packed, the sample does not represent what will ship.
  • Inspecting without a defect list. Without agreed classes, the inspector, the factory and you argue about each defect after the fact.
  • Reading AQL 2.5 as 2.5% of the lot. The acceptance numbers apply to the sample; a lot that passes can still contain defects.
  • Lowering the level to save a day. Level I by default checks fewer pieces and raises the chance that a poor lot passes.
  • Forgetting the critical class. If no one has written down what counts as critical for your market, nothing will be classed critical.
  • Paying the balance before the report. Once the money has left, a failed inspection is information, not leverage.
  • Treating a pass as a guarantee. Every sampling plan carries a consumer's risk. Keep your claims procedure in the contract for defects found later.

Wording for your purchase order

Adapt these clauses to your product and have them checked by your own adviser. Their purpose is to settle the inspection rules before production starts, when you still have a choice of supplier.

  • Inspection: the goods are inspected before shipment by an inspector appointed by the buyer, under ISO 2859-1, single sampling, normal inspection, general inspection level II.
  • Acceptance: AQL 0 for critical, 2.5 for major and 4.0 for minor defects, as classified in the defect list annexed to this order.
  • Tests: function and safety tests on a sample at special inspection level S-3, as listed in the annex.
  • Timing: the inspection takes place when production is complete and at least 80% of the goods are packed. The supplier gives at least five working days' notice.
  • Access: the inspector selects the cartons at random. The supplier provides space, tools, power and staff to open and test them.
  • Payment: the balance is due within ten days of an inspection report with an overall pass.
  • Failure: if the lot fails, the supplier sorts or reworks it at its own cost, and the re-inspection is charged to the supplier.
  • Reference: a sample approved and sealed by both parties is kept at the factory for the inspector.

Inspection checklist

  1. 01

    Fix the reference

    Approve a sample, seal it, and complete the specifications, packaging and labelling instructions.

  2. 02

    Write the defect list

    Each likely defect, its class, a photo of the limit, and how appearance is judged.

  3. 03

    Choose the plan

    ISO 2859-1, general level II by default, AQL per class, and a special level for long or destructive tests.

  4. 04

    Put it in the order

    The plan, the defect list, the payment trigger and the failure path, signed before production.

  5. 05

    Book the inspection

    Against the production schedule: complete and at least 80% packed on the day.

  6. 06

    Brief the inspector

    Send the approved sample reference, specifications, defect list and test list before the visit.

  7. 07

    Read the report

    Quantity found, sampling plan, defect counts against the acceptance numbers, photos and tests.

  8. 08

    Decide

    Pay the balance on a pass. On a fail, sorting or rework, then a new inspection before any payment.

Glossary

TermMeaning
AQLAcceptance quality limit: the quality level a sampling plan is designed to accept most of the time.
LotThe quantity inspected as one unit, usually one order or one production run.
Inspection levelThe setting, from S-1 to III, that decides how large the sample is for a given lot size.
Code letterThe letter given by the lot size and the level, which points to the sample size.
Acceptance number (Ac)The highest number of defects of a class the sample may contain and still pass.
Rejection number (Re)The number of defects of a class at which the lot fails.
Critical, major, minorThe three defect classes: safety or compliance, function or saleability, cosmetic.
LTPDLot tolerance percent defective: a defect level the buyer would find unacceptable.
Producer's and consumer's riskThe chance of rejecting a lot at the AQL, and of accepting a lot at the LTPD.
Pre-shipment inspectionThe inspection of finished, mostly packed goods, usually tied to the balance.

Frequently asked questions